• 1 x ENERCON E 103 E2/2,35MW, hub height 138 m, rotor diameter 103 m.
• An agreement to enter into a contract was signed with ČEZ Distribuce, a.s. regarding connection of 2.35 MW to the existing line 22 kV at a distance of approx. 4.2 km in the cadastral territory Kostrčany behind the border section switch. The electric power will be fed into the substation Podbořany. A prerequisite is that there will be U/Q regulation.
• Consent of the municipality to the investment plan.
• Own plot of land for construction of the wind power plant.
• EIA – Environmental Impact Assessment – approving opinion.
• Planning permission – expected until 4/2020.
• Building permit – expected until 06/2020.
• Construction of the wind power plant in 2021 after amendment of the Act on supported energy sources.
• Expected yearly power generation approx. 5 800 000 kWh.